Timeline
July 1, 2020
The feasibility study planning process for turning basin channel improvements commenced.
December 17, 2021
A draft Integrated Feasibility Report (IFR), which includes compliance with the National Environmental Policy Act (NEPA), was released for public review.
February 14, 2022
Public review period of First IFR closed. USACE requested comments related to the First IFR be submitted.
March 2023
2nd draft Integrated Feasibility Report (IFR), which includes compliance with the National Environmental Policy Act (NEPA), planned for public release
late 2023
The California Environmental Quality Act (CEQA) draft document is anticipated for public review.
June 30, 2024
The feasibility study planning process for turning basin channel improvements is anticipated to conclude.
2024-2026
Tentatively, and subject to change, pre-construction engineering and design (PED).
2027-2029
Construction activity.